储运工程公司完成浙江首座27万立方米低温储罐穹顶吊装

3月16日,储运工程公司承担的浙江LNG三期项目,浙江地区首座27万立方米“桩基式”LNG储罐二标段1号罐顺利完成穹顶吊装,实现了LNG储罐安装工程的重要节点,为今年7月该项目储罐工程实现气顶升奠定坚实基础。

中国海油宁波“绿能港”三期项目是国家储气能力提升的重点建设项目,储运工程公司承担其中3台27万立方米LNG储罐的安装工作。目前,4号罐穹顶正在预制,土建施工正在对第5带墙体钢筋网片进行安装。下一步,项目将按施工计划持续稳步向前推进,确保气顶升等后续关键节点按期实现。(白悦悦)

On March 16th, the storage and transportation engineering company undertook the Zhejiang LNG Phase III project, and the first 270000 cubic meter "pile foundation" LNG storage tank in the Zhejiang region, Section 2, Tank 1, successfully completed the dome lifting, achieving an important milestone in the LNG storage tank installation project and laying a solid foundation for the gas lifting of the project's storage tank engineering in July this year.

The Phase III project of CNOOC Ningbo Green Energy Port is a key construction project for enhancing national gas storage capacity. The storage and transportation engineering company is responsible for the installation of three 270000 cubic meter LNG storage tanks. At present, the dome of the 4th tank is being prefabricated, and the civil construction is installing the steel mesh of the 5th belt wall. Next, the project will continue to steadily advance according to the construction plan, ensuring that key milestones such as gas lifting are achieved on schedule.(Bai yueyue)



信息来源: 
2024-03-20